Selling Flats During Building Refurbishment: When to Start and What Are the Implications

Published 11 November 2026

You can sell flats during building refurbishment provided ownership rights, permits and budget are settled. It makes sense only if the construction budget and flat prices have been confirmed by prior analysis—not if sales are meant to fund a building with uncertain costs. Timing affects cash flow, buyer risk and final property valuation.

Summary

  • Selling during construction is feasible but timing depends on the state of legal preparation, permits and confirmed figures—not on cashflow needs.
  • Unit ownership transfers to the buyer only upon registration in the Czech Land Registry (katastr nemovitostí); until then a preliminary contract and attorney escrow (advokátní úschova) are used.
  • Buyer payments should be transferred securely via attorney escrow and released as conditions are met.
  • Pre-sales can reduce reliance on external financing but increase obligations to buyers if construction is delayed.
  • A feasibility study taking 6 weeks will clarify whether and when starting sales is justified.

Is It Worth Selling While the Building Is Still Being Refurbished?

Yes, provided the sale does not create obligations the building cannot meet at that stage. What matters is whether the final state of the units is clear, whether permits are in place and whether the construction budget is verified.

The main economic incentive to start earlier is significant: the typical value uplift from selling units individually compared to selling the whole building when completed is +20–40 %. The exact figure depends on the specific building's feasibility study. Premature sales with uncertain parameters can harm this added value, because you commit to areas, layouts or timescales you later fail to deliver. You can estimate your project's potential using our property potential calculator.

The Right Moment: Three Gates Rather Than a Calendar Date

Sales start timing is governed by confirmed figures, not construction schedule. The project therefore passes through three gates: legal, permit and sales gate. You only proceed to the next phase when figures are locked in.

  1. Legal gate: verified ownership, encumbrances in the land registry, rental arrangements and the ability to split the building into units.
  2. Permit gate: construction permit or notification under the Building Act No. 283/2021 Coll. and a clear scope of works.
  3. Sales gate: confirmed prices per unit, construction budget and financing method. Only here is the decision made to launch sales.

The full process is described on How It Works. If any gate is not met, selling during construction usually just transfers uncertainty to buyers and eventually back to you.

Legal Framework: What Can Be Sold and When Ownership Transfers

Until a unit is registered in the land registry and the purchase recorded, the buyer does not own it. Ownership of immovable property transfers upon registration in the Czech Land Registry (katastr nemovitostí) under the Land Registry Act No. 256/2013 Coll. The land registry office cannot decide sooner than 20 days after notifying the owner; the average registration time is around 22 days.

Units are created by the owner's declaration under Article 1166 of the Civil Code No. 89/2012 Coll. Whether the declaration can be made during refurbishment depends on the state of construction and the land registry office's requirements, so this must be verified beforehand. Before a unit exists and is transferred, a preliminary contract for sale is typically concluded under Article 1785 of the Civil Code, binding both parties to execute a main purchase agreement at a later date.

The general right of first refusal for co-owners was abolished; it remains only for 6 months from the creation of co-ownership if the share arose through inheritance (Article 1124 of the Civil Code). If the building is owned by multiple persons, resolve this before starting sales.

Buyer Protection and Cash Flows During Construction

Buyer payments before the building is finished must be protected by escrow; otherwise dispute risk and reputational damage grow. Reputable sales are conducted non-cash via attorney escrow (advokátní úschova). Cash payment is also limited to approximately €11,250 per day under Act No. 254/2004 Coll., making it impractical for the full purchase price of a unit anyway.

Best practice for releasing funds:

  • deposits are held in escrow, not transferred directly to the project account,
  • release is tied to verifiable milestones, such as submission of a registration application or completion of a build phase,
  • the contract clearly sets completion date, consequences of delay and the buyer's right of withdrawal,
  • scope (area, layout, specification) is described precisely.

Cash flow is thus slower than selling the whole completed building, but it is predictable and can be evidenced to the bank or project partners.

Impact on Financing and Project Refinancing

Pre-sales can lower the need for external capital but must not replace a missing budget. For a bank or investor, preliminary contracts signal demand, not an unconditional source of funds that can be relied upon.

When planning, pay particular attention to these impacts:

  • Mortgages: if the building is encumbered by a loan, release of units from the security interest must be arranged beforehand or the transfer cannot be completed.
  • Construction delay: each schedule slip will affect relationships with buyers and financing costs.
  • Price: units sold early may be valued lower than when the building is finished, so consider holding back part of the inventory.
  • Tax: real estate acquisition tax was abolished (Act No. 386/2020 Coll.). Impact on income tax from the sale (Act No. 586/1992 Coll.), such as the holding period or primary residence exemption, should always be checked with the Tax Authority (Finanční správa) or a tax adviser.

Depending on the level of capital involvement, various collaboration models may apply, for instance partnership / JV with shared risk.

What to Do Now

First verify the figures and legal position, only then plan the first sale. Prepare these documents:

  1. current extract from the Czech Land Registry (katastr nemovitostí) including any mortgages and encumbrances,
  2. summary of tenancy agreements and occupancy status,
  3. available design documentation, permits and construction budget,
  4. details of existing financing and terms for release of mortgages.

On this basis, a paid audit and plan can prepare a feasibility study with results within 6 weeks. If you wish to delegate the entire preparation and execution under a single agreement, see End-to-End Execution; further answers are in Frequently Asked Questions. Obtain a non-binding offer or property assessment via the form below the article.

Frequently asked questions

Can I sell flats before the declaration of ownership (prohlášení vlastníka) exists? +

Typically, before units are created, a preliminary contract for purchase (smlouva o smlouvě budoucí) is concluded under Article 1785 of the Civil Code No. 89/2012 Coll. Units are created by the owner's declaration under Article 1166 and the transfer will occur only after they exist.

When does the buyer become the owner of the flat? +

Upon registration in the Czech Land Registry (katastr nemovitostí) under the Land Registry Act No. 256/2013 Coll. The land registry office cannot decide sooner than 20 days after notifying the owner; the average registration time is around 22 days.

Can I accept a cash deposit from the buyer? +

Cash payment is limited to approximately €11,250 per day under Act No. 254/2004 Coll. Reputable sales are conducted non-cash via attorney escrow (advokátní úschova), which protects both sides.

Is it worthwhile to sell units individually instead of the whole building? +

The typical value uplift is +20–40 %; the exact figure depends on your building's feasibility study. Tax implications for income on the sale should always be verified with the Tax Authority (Finanční správa) or a tax adviser.

Sources

This article is for information only and is not legal advice. Reviewed 11 November 2026.