What to do if you discover part of the building is not registered in the Czech land registry during transformation
Published 22 November 2026
If an audit reveals that part of a building is not registered in the Czech Land Registry (Katastr nemovitostí), do not proceed with drafting the owner's declaration or selling units until the discrepancy is resolved. First, determine what type of discrepancy exists — unregistered extension, missing plot or incorrect registry data — and choose the appropriate route to register or correct the entry. The discrepancy can usually be resolved as part of the legal transformation process, but it extends the timeline and increases costs that must be understood before moving to the next phase.
Summary
- An unregistered building part must be resolved before the owner's declaration is submitted and before units are sold.
- First, verify the nature of the discrepancy: unregistered extension, missing plot or incorrect registry data.
- The discrepancy typically requires a geometric plan (geometrický plán), building documentation and possibly retroactive permission under the Building Code (Stavební zákon) No. 283/2021.
- Resolution delays the timeline and increases costs; the next phase begins only with confirmed figures.
- The earlier the discrepancy is detected, the smaller its impact on the transformation.
Why a land registry discrepancy is critical for transformation
Transformation relies on units being clearly defined and registered in the Czech Land Registry, so the actual condition of the building must match the records.
A building is divided into individual units (jednotky) through an owner's declaration under § 1166 onwards of the Civil Code (Občanský zákoník) No. 89/2012. Ownership of real property is transferred only upon registration in the Czech Land Registry (Katastr nemovitostí) under the Land Registry Act (Katastrální zákon) No. 256/2013. If part of the building is recorded incorrectly or not at all, it cannot be reliably included in the units nor sold safely. A buyer, their bank, and their lawyer will all verify the registry status, so discrepancies will usually be discovered by the time of sale.
Detecting the issue in an audit is therefore valuable: the problem is solved before any obligation to buyers arises.
What types of discrepancies occur in practice
The procedure differs depending on what exactly is missing from the registry, so the first step is accurate diagnosis.
| Type of discrepancy | Example | Typical solution |
|---|---|---|
| Unregistered building modification | Extension, additional storey or internal alteration without registry registration | Documentation of legal status, possibly retroactive permission; survey and registration of change |
| Missing or incorrect plot | Part of built or paved area registered differently than reality | Geometric plan, possibly resolution of property ownership |
| Incorrect registry data | Wrong use classification, area or building designation | Correction of error in registry records or notification of data change |
| Disputed ownership | Building part registered to another owner or with no registered owner | Resolution of ownership rights, possibly court proceedings |
Under the Civil Code (Občanský zákoník) No. 89/2012 (§ 506), a building connected to land by a permanent foundation is not part of the plot of land as such, but this does not mean it can be unregistered. The boundary between a registry error and a genuinely illegal structure is a legal question that must be assessed based on documentation and the building's history.
Step-by-step procedure
The discrepancy is resolved in a fixed sequence to avoid unnecessary spending on steps that might need to be repeated.
- Verify the registry status. Request a current extract from the ownership sheet and copy of the cadastral map, and retrieve available documents from the registry archive if needed.
- Compare records against reality. A survey or technical assessment is needed to determine what exactly is missing or recorded incorrectly.
- Retrieve building documentation. This includes building permits, completion certificates, design documentation and any later modifications.
- Assess legality. If the building lacks required permission, retroactive permission under the Building Code (Stavební zákon) No. 283/2021 may be an option; the building authority decides and the outcome cannot be guaranteed in advance.
- Prepare registration documents. Depending on the discrepancy, this includes a geometric plan (geometrický plán), documents proving ownership or a request to correct registry data.
- Submit application to the land registry. The registry authority cannot decide earlier than 20 days after notifying the owner (Land Registry Act No. 256/2013); average registration time is around 22 days.
- Verify the new status. Only after successful registration do you proceed with drafting the owner's declaration and defining the units.
If steps involve property ownership (such as disputed ownership), expect longer timelines than for simple data corrections. Specific deadlines depend on the authorities and case complexity.
Impact on timeline and costs
Adding a registry entry extends the transformation and increases costs, but it is better resolved during the legal phase than at sale.
A project moves through three gates: legal, permit and sales. The next phase begins only with confirmed figures. A registry discrepancy sits in the legal gate: until it is resolved, you cannot confirm how many units will be created or their size, and therefore cannot confirm the revenue from resale. The typical value difference between selling a building as a whole and unit-by-unit is +20–40 %, but the exact figure depends on the feasibility study. If part of the building is missing, the number and size of units may change, and therefore this outcome too.
Costs mainly comprise:
- Survey and geometric plan (geometrický plán),
- Technical assessment and documentation of actual condition,
- Administrative fees and possible building authority proceedings,
- Legal services,
- Possible structural work if the current state cannot be legalised as-is.
The total cost cannot be stated in general terms; it depends on the scope of the discrepancy and whether the building can be legalised. It is therefore wise to include a reserve in the budget and allow the timeline for possible delays with the authorities. A rough idea of the building's potential is provided by the potential calculator, but binding figures emerge only from the feasibility study.
Legal risks and what to avoid
The greatest risk is proceeding with transformation as if the discrepancy did not exist.
- Rejection or suspension of proceedings. An owner's declaration that does not reflect the actual and registered state may be rejected by the registry or proceedings may be suspended.
- Illegal building. If part of the building was constructed without permission and cannot be retroactively permitted, the building authority may issue an order under the Building Code (Stavební zákon) No. 283/2021. The outcome depends on the specific case.
- Liability to buyers. Sale of a unit with a defective legal status may give buyers rights under the Civil Code (Občanský zákoník) No. 89/2012.
- Unclear ownership. If the discrepancy reveals that part belongs to another party, ownership rights must be resolved first.
Do not rely on informal agreements or assume buyers will not notice the discrepancy. The actual state must be brought into line with the records, not the other way round.
What to do now
Have the discrepancy professionally assessed before deciding on further investment in the project.
- Prepare a current extract from the ownership sheet, the cadastral map and any available building documentation (permits, completion certificates, plans).
- Gather information about the building's modification history: when and by whom were changes made.
- Record exactly what the audit found, including photographs and measurements.
- Pause any actions creating obligations to third parties, such as preliminary sales agreements for units.
- Have the discrepancy assessed legally and technically as part of the Audit and Plan; delivery is within 6 weeks.
If you are unsure whether this applies to you, an overview can be found on the Who is Činžáky.com for page; further context is in the blog. You can get a non-binding offer or assessment via the form below the article.